1. Three types of calculations
1.1. Earned value management
abbreviation | Calculation formula | Main test points |
---|---|---|
budget at completion BAC | completion budget | |
Plan value PV | PV = BAC * Planned work done % | Planned workload to be completed |
actual value EV | EV = BAC * % of actual work completed | Actual amount of work completed |
Actual cost AC | Actual cost | |
Cost Variance CV | CV = EV - AC | Greater than 0 good |
Progress deviation SV | SV = EV - PV | Greater than 0 good |
Completion Variance VAC | VAC = BAC - EAC | Greater than 0 good |
cost performance indexCPI | CPI = EV / AC | Greater than 1 good |
Schedule Performance Index SPI | SPI = EV / PV | Greater than 1 Good SPI and critical paths |
Estimate at Completion EAC | EAC = AC + ETC | atypical performance |
Estimate at Completion EAC | EAC = BAC / CPI | typical performance |
ETC needs to be estimated upon completion | ETC = BAC - EV | atypical performance |
ETC needs to be estimated upon completion | ETC = (BAC - EV) / CPI | typical performance |
ETC needs to be estimated upon completion | ETC = (BAC - EV) / (CPI * SPI) | rush work |
To-Complete Performance Index TCPI | TCPI = (BAC – EV) / (BAC – AC) | as planned |
To-Complete Performance Index TCPI | TCPI = (BAC - EV) / (EAC - AC) | Baseline change |
1.2. Key path calculation & three-point estimation
Knowledge points | Test points |
---|---|
Critical Path Calculation - Critical Path | The longest path of the project |
Critical Path Calculation - Total Float | The activity starts (ends at the latest) - the activity starts (ends at the earliest) |
Critical Path Calculation – Free Float Time | The next activity starts earliest - the current activity ends earliest - 1 |
Key path calculation - four logical relationships | finish - start, start - finish start - start, finish - finish |
Three Point Estimate - Expected Value | (most optimistic + 4 most likely + most pessimistic) / 6 |
Three point estimate - standard deviation | (most pessimistic - most optimistic) / 6 |
1.3. Decision tree analysis & EMV calculation
EMV (expected monetary value) = P (percent) * V (value)
2. Four types of processes
2.1. Quality management process
- See "Process Quality Control" and select [Quality Assurance]
- When you see "Result Quality Check", select [Quality Control]
- See "Quality Standard Inspection and Correction" and select [Quality Assurance]
- When you see "Product Problem Inspection and Correction", select [Quality Control]
- See "Development of Quality Standards" and select [Quality Planning]
2.2. Process related to deliverables
- See "Internal Acceptance Results" and select [Quality Control]
- When you see "Customer Acceptance Results", select [Confirm Scope]
- See "Outputs" and select [Guide and manage project work]
- When you see "Results Transfer", select [End Project or Phase]
2.3. Communication management process
- When you see "Determine the method/content of information transmission", select [Plan Communication]
- When you see "Ensure successful delivery of information", select [Manage Communication]
- When you see "Optimize information transfer process", select [Supervise Communication]
2.4. Stakeholder management process
- See "Identify Stakeholder Interests, Expectations and Influences" and select [Identify Stakeholders]
- When you see "Implement management strategies to minimize resistance", select [Manage stakeholder engagement]
- When you see "Adjust management strategies", select [Supervise the participation of relevant parties]
- See "Management strategies developed to mobilize stakeholder participation" and select [Planning stakeholder participation]
3. Five major processes
3.1. Risk management process
- Plan risk management --> Identify risks --> Qualitative risk analysis --> Quantitative risk analysis --> Plan risk responses --> Implement risk responses --> Monitor risks
- Risk process test points, updating the risk register has the highest priority
3.2. Risk implementation process
[External link image transfer failed. The source site may have an anti-leeching mechanism. It is recommended to save the image and upload it directly (img-nFLHNsiQ-1655692046778)(http://192.168.1.218:1901/server/index.php?s=/ api/attachment/visitFile/sign/6254e78a9bf0d8881b2b3e7dd1b861e2&showdoc=.jpg)]
3.3. Problem management process
- Identify the problem --> Record the problem --> Analyze the problem --> Solve the problem --> Change the process
- Problem process test points, updating the problem log has the highest priority
3.4. Change process
[External link image transfer failed. The source site may have an anti-leeching mechanism. It is recommended to save the image and upload it directly (img-tixUWOaz-1655692046780)(http://192.168.1.218:1901/server/index.php?s=/ api/attachment/visitFile/sign/a7065323eef55f8d4704bd7c9dc19bd6&showdoc=.jpg)]
3.5. Closing process
- Beginning --> Final acceptance of the project, confirming achievement of project scope -- (no changes since) --> Transfer of ownership of deliverables --> Financial, Legal and Administrative Closure --> Release of final project report, completion of work performance evaluation -- -> Organize experience and lessons, conduct comprehensive project assessment --> Archive for future project audits --> Feedback from event stakeholders, investigate stakeholder satisfaction --> Hold a celebration banquet and dismiss team members --> End
4. Six major tools
4.1. Process problem solving tools
- When you see "Progress is delayed, resources and costs are increased", select [Catch up]
- When you see "Progress postponed, order changed to parallel", select [Quick Follow]
- When you see "Quality issues found in deliverables", select [Testing/Product Evaluation]
- When you see "There are problems in the project process", select [Quality Improvement Methods]
- When you see "Adjust the start time of subsequent activities", select [Advance and Lag]
- When you see "Dispute with Supplier", select [Claim Management]
- When you see "Making decisions on project-related business", select [Project Governance]
- When you see "Comply with internal and external rules of the organization", select [Compliance]
4.2. Personnel problem solving tools
- When you see "Low remote efficiency", select [Centralized Office]
- When you see "Teams are distributed in different regions", select [Virtual Team]
- When you see "Insufficient Personnel Capacity", select [Training]
- When you see "Promote trust among personnel", select [Team Building]
- When you see "Staff transitional use and hope not to delay", select [Resource Smoothing]
- When you see "Staff transition, progress may be delayed", select [Resource Balancing]
4.3. Communication management tools
- When you see "Communicating a large number of personnel information", select [Communication method: pull communication]
- When you see "Email Delivery Information", select [Communication Method: Push Communication]
- When you see "Two-way communication such as video conferencing", select [Communication method: interactive communication]
- When you see "Information transmission is not smooth enough", select [Communication Needs Analysis]
4.4. Risk response tools
- See "More Testing/More Reliable Suppliers/Redundant Components" and select [Risk Mitigation]
- When you see "Buy insurance or outsource", select [Risk Transfer]
- When you see "Remove risky work packages/cancel projects", select [Risk Avoidance]
- When you see "Arrange time and resources as emergency reserves", select [Risk Acceptance]
- When you see "Natural Disaster", select [Risk Report]
- When you see "Establish a risk-sharing cooperation method", select [Risk Sharing]
- When you see "Increase Resources", select [Risk Enhancement]
- See "Improve technology to save costs and shorten schedule" and select [Risk Development]
4.5. Interpersonal relationship and team skills tools
- When you see "Team members respect cultural differences", select [Cultural Awareness]
- When you see "The ability to manage emotions", select [Emotional Intelligence]
- See "Ability to influence relevant parties/stakeholders" and select [Influence]
- When you see "Encourage the team and improve team capabilities", select [Leadership]
- When you see "Team Member Formation", select [Negotiation]
- When you see "Agree Agreement", select [Cooperation/Problem Solving]
- When you see "Both parties are satisfied to a certain extent/each takes a step back", select [Compromise]
- When you see "One party convinces the other party/Seeks common ground while reserving differences", select [Relaxation/Tolerance]
- When you see "Ease conflicts and temporarily put them on hold", select [Retreat/Avoid]
- When you see "Tight time, big impact", select [Force/Command]
4.6. Schedule/cost estimation tools
- When you see "Compare Similar Projects", select [Analogous Estimate]
- When you see "Experts give methods and conclusions", select [Expert Judgment]
- When you see "Most Accurate Estimate", select [Bottom-up Estimate]
- When you see "Consider risks and uncertainties", select [Three-point estimation]
- See "Using Historical Data Statistical Technology" and select [Parameter Estimation]
5. Seven major data tools
5.1. Data collection tools
- When you see "Compare with comparable organizations", select [Benchmarking]
- When you see "One-on-one communication", select [Interview]
- When you see "Face-to-face brainstorming", select [Brainstorming]
- When you see "Subject Experts Conduct Discussion", select [Focus Group]
- When you see "Multiple people quickly collect information", select [Questionnaire]
- When you see "Select a small number of samples for testing", select [Statistical Sampling]
- When you see "Verify whether a series of steps have been executed", select [Checklist]
- When you see "Collect useful data about potential quality issues", select [Checklist]
5.2. Quality analysis tools for data analysis
- When you see "Quality Training or Process Documentation", select [Prevention Cost]
- When you see "Test or Inspection", select [Evaluation Cost]
- When you see "Rework or Scrap", select [Internal Defect Cost]
- When you see "Warranty or Business Loss", select [External Defect Cost]
- When you see "The cost of investing in quality is too high", select [Cost-Benefit Analysis]
- When you see "Identify non-value-added activities", select [Process Analysis]
- When you see "Find the root cause of the problem", select [Root Cause Analysis]
- When you see "Optimize design to improve final product characteristics", select [Design for X]
5.3. Risk analysis tools for data analysis
- See "Risks caused by constraints or restrictions" and select [Assumptions and Constraints Analysis]
- See "Comprehensive Identification of Risks" and select [SWOT Analysis]
- See "Risk Classification Sorting" and select [Probability and Impact Assessment]
- See "Evaluate the validity of risk basic data" and select [Risk Data Quality Assessment]
- See "Evaluate the ratio of risks to contingency reserves" and select [Reserve Analysis]
- See "Quantitative Risk Ranking" and select [Sensitivity Analysis]
- When you see "Use models to determine the impact of risks", select [Simulation]
- See "Risk Decision" and select [Decision Tree]
5.4. Data analysis and procurement analysis tools
- When you see "Discuss whether to make it yourself or outsource it", select [Make it yourself and outsource it]
- When you see "Evaluate whether a potential seller wins the bid", select [Proposal Evaluation]
- When you see "Methods for selecting suppliers", select [Supplier Selection Analysis]
5.5. Performance analysis tools for data analysis
- See "Project Baseline and Actual Comparison" and select [Deviation Analysis]
- See "Estimation of the future form of the project" and select [Trend Analysis]
- When you see "Verify Deliverables", select [Check]
- When you see "Verify whether the seller's performance complies with the contract", select [Performance Review]
- When you see "Verify whether the selected seller's process is compliant", select [Audit]
- See "Analyze gains and losses of the project" and select [Regression Analysis]