Habits to develop and clock in-Chapter 8 Project Quality Management

1. Project quality management needs to take into account both () and ()
A. Project management and project deliverables
B. Quality requirements and quality standards

2. Describes "the degree to which a series of intrinsic characteristics meet the demand" is
A. Quality
B. Grade

3. Indicate the location of the result on the continuous scale and indicate the degree of qualification. What does this describe?
A. Variable sampling
B. Attribute sampling

4. The work of managing quality belongs to () in the framework of quality cost ()
A. Consistent work
B. Inconsistent work

Reference answer

A A A A

Guess you like

Origin blog.csdn.net/qq_33790600/article/details/114836305