New Production Forecast

Run MRP calculation

MRP planned Order Maintenance

Kitting query

New Production Forecast

Case

erplabs machine company in October based on product planning and market forecasts, the following new Production Forecast in ERP.

product name

Number forecast

Forecast start date

Predicted end date

A black finished

1000

2017-10-10

2017-10-30

A finished White

1000

2017-10-10

2017-10-30

H Gold finished

1500

2017-10-10

2017-10-30

Double-click to enter the next screen

Elected to the material code, with names, specifications, project, predict the number of entry start date, end date forecast. Save review.

Run MRP calculation

Case

According to the new forecast single-step data, planners calculate running MRP ERP system generates planned orders.

product name

Number forecast

Forecast start date

Predicted end date

A black finished

1000

2017-10-10

2017-10-30

A finished White

1000

2017-10-10

2017-10-30

H Gold finished

1500

2017-10-10

2017-10-30

Double-click to enter the next screen

Click Next, go to the next screen

The first point of the low maintenance code, return to the current interface When finished, click Next, go to the next screen

No automatic generation operation, the program operation button next point is selected from the MRP01 (see background configuration), click Next, advance to the next screen

Point selection button, following interface pops

Select the required line, point return, return to the following interface

Click Next, go to the next screen

Click Next, go to the next screen

The system started MRP calculation is completed, the next screen display

Point Finish to complete and exit the MRP calculation functions

Order Maintenance Plan

Case

MRP calculation step to generate the raw materials, the committee member, semi-finished products planned order, and auditing served by this operation step, Purchase Requisition module generates purchase, production module production order.

Double-click to enter the next screen

Display the latest operation ID encoding MRP calculation, the latest copy to the left encoding MRP calculation, the document state and the closed off mode as shown above check point is determined, the next screen to enter

Can see the status column is a "plan", material types include: homemade, subcontract, procurement, program the number of orders have been merged, select all the rows, the audit points, and then select all the rows, point delivery, the following picture appears

You can see the delivery status column is "closed."

Display generated purchase requisitions

You can see the type of business including outsourcing warehousing, outsourcing orders for generating purchase orders and outsourcing, and the same type are combined into a purchase requisition.

Display generation MO

Can see the status of the document is "program", it is a common type of production orders (not rework orders), MRP generated source documents.

Kitting query

Case

Before production orders can be issued, the relevant production of finished products, semi-finished products - sets of materials query through this function.

Double-click to enter the next screen

BOM expand the options selected fully deployed, the type of material gathering summary of all selected materials, detailed button points, following a pop-up interface

 