The real questions for the thesis exam of "Information System Project Manager" in the second half of 2021

Information system project manager in the second half of 2021

"Thesis Topics"

Test Question 1: On the Bidding Management of Information System Projects

Bidding management is a method of selecting the best deal in an organized way by applying the method of technical economy and the competitive function of market economy.

Please discuss with the title "On the Bidding Management of Information System Projects":

  1. Briefly describe an information system project you have participated in and manage (project background, project scale, sponsoring unit, purpose, project content, organizational structure, project cycle, delivered results, etc.), and explain the work you undertake in it, (project The background requires my real experience, no plagiarism or fabrication)

  1. Please combine the information system project you described, discuss your understanding of information system project bidding management around the following points, and summarize your experience.
    1. The process of project bidding management
    2. Based on the project you describe, prepare a scoring sheet for tender documents

  1. Please combine the project bidding management and bidding documents you described, and write down the matters needing attention in the process from bidding document preparation to delivery

Test Question 2: On the Progress Management of Information System Projects

       Project schedule management is to manage the progress of each stage and the final completion deadline during the project implementation process. Its purpose is to ensure that the project can achieve its overall goals under the premise of meeting the time constraints.

Please discuss with the title of "Schedule Management of Information System Projects":


1. Briefly describe the information system project you participated in the management process (project background, project scale, initiator, purpose, project content, organizational structure, project cycle, delivered results, etc.), and explain the work you undertake in it (project background I am required to have real experience, no plagiarism or fabrication).

2. Based on the information system project you described, please discuss your understanding of the progress management of information system projects around the following points, and summarize your experience:

  1. The process of project schedule management;
  2. If schedule delays occur during the schedule management process, please provide solutions based on practice;

3. Please use the Gantt chart to prepare a corresponding project schedule based on the information system project you described.