The operational requirements see: https://edu.cnblogs.com/campus/nenu/2019fall/homework/9958
Team name: "Leader" group
Leader: Yang Tianyu
Members: Wei Xin, Romania Yangmei Hui, Wang Xin Yao, plum rain
The Master: Yang Tianyu
One: Scrum witness
Requirement 1: Work Photo
Requirement 2: the time span, to the minute, when to start and when to end
At 11:25 on November 11, 2019 to 11:53 hours, a total of 28 minutes.
Requirement 3: Location
School of Information Science and Technology, 107 classrooms
Requirement 4: legislature content
Yesterday's results: the development of the code specifications, each optimized code.
Today's plan: to add new functionality to test to find the problem.
At present difficulties: activities which added a few good pictures at the same time appear.
Requirements 5: todo list
II: burndown
leangoo billboards link: https://www.leangoo.com/kanban/board/go/3087061#
Three: Version Control