Legislative Council Report of victory points 20191010-6 alpha week 1/2 Scrum + burn 04

This job requires See: https: //edu.cnblogs.com/campus/nenu/2019fall/homework/8749

First, the case team
leader: He Jingwen
Members: Peng Siyu Yang Ping Wang Zhiwen bit barracks
Team name: Victory Point

Two, Scrum regular
Time: October 13, 2019
The Scrum Master: Peng Siyu

1 requires  work photo

 

2 requires  time span

At 9:07 on October 13, 2019 to at 9:39 on October 13, 2019

Total 32 minutes

Requirement 3  locations

Northeast Normal University cafeteria on the second floor across from a tea table.

Requirements 4  Legislative Council include:

(1) Yesterday's results

1. Complete js interaction (mass participation issue).
2. To achieve page jump (election-related issues).

(2) Today's plan

1. Discuss Ways to learn the code.

2. The report project progress.

3. Discussion rules of the game interface and how to contact us interface

(3) current difficulties

1. How to write software for micro-channel customer dialogue to achieve a small program with the keyboard.

2. How riddle does not need to hide.

3. how to solve the user-friendliness (how to fill out all at once when the user fill in words)

4. how to merge the multi-part code.

Requirements 5  TODO List

Task ID

task

Mandate holders

deadline

status

1

October 10 is determined daily and regular meeting time and place of the meeting master

Yang Ping

October 10, 24:00

completed

2

Discuss the contribution allocation

Holder

10 May 16 20:00

processing

3

Personnel assigned master

Holder

October 10, 24:00

completed

4

October 11 Scrum legislature plus burndown report

Bit barracks

October 11, 24:00

completed

5

October 12 Scrum legislature plus burndown report

Wang Zhiwen

October 12, 21:00

completed

6

October 13 Scrum legislature plus burndown report

Peng Siyu

October 13, 24:00

completed

7

October 14 Scrum legislature plus burndown report

He Jingwen

October 14, 24:00

Not been

8

October 15 Scrum legislature plus burndown report

Yang Ping

October 15, 24:00

Not been

9

October 16 Scrum legislature plus burndown report

Peng Siyu

October 16, 24:00

Not been

10

Alpha division of the discussion group stage

Holder

10 May 16 20:00

Not been

11

Alpha team decided to stage the division of labor

Holder

10 May 16 20:00

Not been

 

Third, burndown


1 requires the use of [ https://www.leangoo.com/ ].

2 requested daily updates and reports to the Legislative Council published on the same blog.

3 is consistent with the longitudinal Scrum todo list report function portion, i.e., burn-function point and the ordinate the number todo same task list, perform the same function has burndown point and number of tasks completed todo list.

Leangoo billboards link: https: //www.leangoo.com/kanban/board/go/3034232

 

 

 