Read and create broken camp - Sprint log (the next day)

First, the job description

This work belongs courses 2019 Autumn Tai Fook practice of software engineering class Z
Where the job requires Teamwork fifth - Project sprint
Team Name Read and create broken camp
The target job Sprint log (the next day)
Text of the job Read and create broken camp - Sprint log (the next day)
Reference material Development station B video days Ge Anzhuo

Two, SCRUM part

1. Members of the description

No. Crew Today the situation Tomorrow Plan
Task Spend time the remaining time Problems encountered solved problem
1 Sujie Long Similar analysis of actual projects, development of learning 3h 5 days Reference projects flash back portion functions Reference project debug Brushing lesson
2 Chen Yidong Home page, search interface 6h 5 days RecycleView underline show abnormal events can not click on the search list RecycleView underline show abnormal The remaining interface
3 Lin Tao A portion of the suspension button 6h 5 days Imported items as well as some problems can not run You can successfully execute code The remaining part
4 Liuxin Yao Complete interface settings, personal information in the interface 7h 5 days Layout component can not be moved, the title bar has always existed, item jump method Adjust the layout of components, cancel the default title bar, item jumps interface The remaining interface
5 LU Yu Fei Android Development Learning 5h 5 days sdk version is too low, his teammates can not run the code Download the latest version Andrews continues to develop learning
6 Blue Sky Bird Android Development Learning 4h 5 days Do not understand how a APP Basic use development tools Continue to follow the tutorial to learn
7 Lin Zhen Android Development Learning 6h 5 days Andrews storage file Andrews storage file Editing text debris collection
8 Huang Shuyun Learning Android development, writing log 2 6h 5 days No No Continue to learn, to write the log 3

2, some progress screenshots

1、


2、

3, photo SCRUM meetings

4, project procedures / modules of the latest (run) Screenshot



Three, PM report

1、

content time
The entire project is expected to amount of tasks 185h
Now spend time 33h
Also remaining time 152h

2, burndown

In a number of tasks as a unit

In units of time

3, the total task changes the line

4, member contributions than in the case

No. Crew The proportion of the workload
1 Sujie Long 14%
2 Chen Yidong 14%
3 Lin Tao 13%
4 Liuxin Yao 13%
5 LU Yu Fei 11%
6 Blue Sky Bird 11%
7 Lin Zhen 11%
8 Huang Shuyun 13%

Attachment: division screenshot