PMP - Risk Identification of risk register

PMP - Risk Identification of risk register

In the first 200 exam simulation questions, concerning the risk register of all four title wrong, it is necessary here to review the record and more than a few times. (17 July 2019)

1. The risk register

The risk register record details of an individual project risk has been identified. With the implementation of qualitative risk analysis , planning and risk response , implement risk response and supervision of risk to carry out the process, the results of these processes have in mind into the risk register.

Upon completion of the risk identification process, risk register content may include (but are not limited to):

1.1 a list of identified risks

Register at risk, the risk for each individual item is given a unique identification number. To the extent necessary to carry out a detailed description of the identified risks and ensure a clear understanding. Risk can use structured description of risk to distinguish itself with the cause of risk and risk-affected zone.

1.2 persons responsible for the potential risks

If you have identified potential risks responsible for identifying risks in the process, it is imperative that persons responsible for recording the risk register. Followed by the implementation of qualitative risk confirm the analysis process.

1.3 list of potential risk responses

If you have identified some potential risk response measures in the process of identifying risks, you should record it in the risk register. Subsequently confirmed by the risk response planning process.

According to the provisions of the Risk Management Plan risk register format, it may also record other data about each identified risks, including:

  • The risk of short names,
  • Risk category,
  • The current risk status,
  • One or more reasons,
  • The impact on one or more of the target,
  • Risk of triggering conditions (events or conditions that show the risk of imminent),
  • Affected WBS components,
  • And time information (when risk identification, may occur when, when it may no longer be relevant, as well as deadlines for action)

2. Related Exercises

2.1 times the risk, to implement 风险登记册mitigation plans on

20, [radio] a low-probability / high-impact technical risk occurred. The project manager should be how to do?
A low probability / high impact technical risk occurs. What should the project manager do?

A: submit change requests to adjust the cost and schedule baseline Submit a change request to adjust the cost and schedule baselines,

B: risk review to assess its impact on project deliverables Conduct a risk review to evaluate its impact on project deliverables

C: implementation risk register outlined mitigation plans Implement the mitigation plan outlined in the risk register.

D: Query lessons learned knowledge base for possible risk mitigation options Consult the lessons learned repository for possible risk mitigation options.

The correct answer: C; your answer: D

Analysis: Reference Answer: C Resolution: To deal with the risk. Analysis of risk does not exclude B; A, not necessarily; D based on wrong and should inquire risk register.


Risk of 2.2 (third-party) should be updated 风险登记册uncontrollable risk factor is not a problem?

70, [radio] program manager receives notification that the resources allocated to the customer site location within the next two weeks will not be available from third-party vendors. Project Manager which document should be updated? A project manager receives notification from a third-party vendor that the on-site assigned to the client location will be unavailable for the next two weeks. What document should the project manager update?

A: problems logging log Issue
B: Team Assignments' Task Team
C: risk register the Register Risk
D: Responsibility Assignment Matrix (RAM) Responsibility assignment matrix (RAM )

The correct answer: C Your Answer: A

Analysis: Answers: C analysis: risk, risk register updated (and implement mitigation plans outlined in the risk register) . This problem is not a problem, because it is the cause of a third party, belongs to uncontrollable factors.


2.3 For 不确定性i.e. 风险, recording risk register should

75, [Radio] - project team members bit inaccurate critical acceptance criteria challenged other members pointed out inaccuracies may reduce the quality of key deliverables. The project manager should record the issue in which document? Project Team Member challenged OTHER A ON Inaccurate Members Critical Acceptance Criteria, pointing OUT that INACCURACIES could the reduce at The Critical at Quality of deliverables. Which the Document at The Project Manager Should the Document the this Issue?

A: Register parties register the Stakeholder
B: Diagram Ishikawa diagram of Ishikawa
C: mass checklist checklist Quality
D: risk register Ride register

The correct answer: D Your Answer: C

Analysis: Reference Answer: D Analysis: "uncertainty" that risk, should be recorded in the risk register .

I think the time trial title, this is the uncertainty about the acceptance criteria, it should be associated with quality, so choose C.

Quality checklist Quality Checklists: whether to verify the sequence of steps required structured tool has been performed. Checklist that includes items to be considered, or action points list. It is often used as a reminder.

In summary Quality Control (8.3.1) mentioned: a structured checklist helps manage quality control activities. Nothing seems with uncertainty.


One strategy is to avoid the risk of 2.4 is specified on the risk register 风险责任人

79, [Radio] - a risk become a reality at the project site, this risk is recorded in the risk register, the investigation team concluded that, if the proper risk management, this can prevent this risk. To 避免this question, the project manager should do in advance? A risk was realized on site for a project.This risk was recorded in the risk register.The investigation team concludes that the risk could have been prevented if proper risk management had been performed.What should the project manager have done to avoid this?

A: review of lessons learned from past projects Lessons Learned Select this item from Previous the Projects Reviewed
B: update existing risk management programs at The existing Risk Management Plan Updated
C: to the matter at The items designated as responsible for Assigned risk owners risk on the risk register on the risk the Register
D: for himself to mitigate the identified risks to create action created risk mitigation action for the identified risks

The correct answer: C; your answer: D

Analysis: Answers: C Analysis: risk identification, but did not lead to management, most likely because there is no risk of liability assigned people to develop and implement response plans . 题干为“为避免”,D排除, AB and avoid not necessarily logical relationship, C is typical PMP logical choice answers.