1. Multiple choice questions

1. When estimating the progress of a task, A is an optimist and it is estimated to be completed in 6 days, B is a pessimist and it is estimated to be completed in 24 days, and C is an experienced person who thinks it is most likely to be completed in 12 days, then this task is What is the probability that the duration estimate is between 10 days and 16 days?