Software Project Management: PERT duration estimation method

Title: The following flow chart and project task duration following table gives estimates using PERT method of estimating the probability of the completion of the project to obtain 14.57 days

Task \ estimated value The most optimistic Most likely The most pessimistic
A 2 3 6
B 4 6 8
C 3 4 6

EA = (2 + 3 * 4 + 6) / 6 = 20/6 and EB = (4 + 6 * 4 + 8) / 6, E = (3 + 4 * 4 + 6) / 6

∂ = (value pessimistic - optimistic value) / 6

A=4/6、B=4/6、C=3/6

Seek sum

E = EA + EB + EC = 13.5

∂=(∂A^2+∂B^2+∂C^2)^1/2=1.07

According to the law 3∂

Interval Probability
(E , E + ) 0.6826
(E-2 , E 2 + ) 0.9544
(E-3 , E + 3 ) 0.9974

According to the high school knowledge do the math!

 

 

 

 

 