The second half of 2018 systems integration project management engineer afternoon Zhenti questions and answers Case

The second half of 2018 systems integration project management engineer afternoon Zhenti questions and answers Case

【first question】

Resolution:

[Question 1] (8 points)
1, there is a problem on the overall management, project management plan has not been reviewed.
2, there is a range of management issues, there is no need for a detailed analysis with stakeholders, only began after the preliminary understanding of customer needs.
3, there is a change management problem, not change according to the change management process handle
4, schedule management problems, leading to progress is seriously lagging behind.
5, there is communication and management problems, leading to customer dissatisfaction and complaints of the project is, and is not related to project performance data will be sent to the Project Management Office
6, the company projects a lack of guidance and monitoring.

[Question 2] (5 points)
1, the establishment of the organization within the project management support environment
2, training of project management staff
3, to provide project management guidance and counseling
4, multi-project within the organization to manage and monitor
5, Project Portfolio Management
6 improve organizational project management capability

[Question 3] (5 points)

(1 pair

(2) wrong

(3) to

(4) to

(5) wrong

[Second question]


Resolution:

[Question 1] (12 points)
1, Deadline problem, the project legally subject to bidding, bidders from 8 until tender documents are sent out of the filing date of the deadline for the tender documents, which shall not be less than 20 days.
2, bidding agency rejected the bid file modification problems, bidders in the tender documents before the deadline for submission of bid documents may supplement, modify or withdraw the bid documents submitted and notify the tenderer in writing.
3, the scheduled opening time delayed problems, the opening of tender documents should be submitted at the same time the deadline in the tender documents open to the public;
4, there is a problem to accept the late bid c materials company, submission of bid documents requested in the bidding documents deadline after time delivery of tender documents, the tender should be rejected.
5, no successful candidate ranking, after the evaluation is completed, the bid evaluation committee shall submit a written report on bid winning list of candidates to the tenderer. The successful candidate should not be more than three, and indicate the sort.
6, A Company D Company won the bid directly determines there is a problem, the tenderer shall determine the number one successful candidate for the winning bidder.
7, A Company announced successful results, and issued a notice of problems D company won the bid after winning bidder is determined, the successful tenderer shall send a notice to the winner, while the winning inform all unsuccessful bidders of.
8, B Company asked the successful outcome to the tendering agency, the bidding agency refused to inform secrecy. Need to be successful inform all unsuccessful bidders of
9, A and D companies signed a commercial contract problems, the tender bid and the winning bidder shall, from the date of issuance of the notice within thirty days, in accordance with the tender documents and the winning bidder tender documents conclude a written contract.
10, D will work an important project subcontracted to another company there is a problem, only the non-body, non-critical work.
11, there is a problem directly subcontracting company D projects, the main part of the non-winning bidder or by the consent of the tenderer may be winning the contract in accordance with the project, and critical work subcontracted to others to complete.
12, project implementation may not be fully prepared too hastily.

[Question 2] (3 points)
tender invited bids (IFB), request for proposal, (RFP), Request for Quotation book (RFQ) and recommended books

[3] Problems (2 minutes)
A
D

The third question [slightly]

[Fourth Title]

Resolution:

[Question 1] (10 points)
1, lack of senior management awareness of quality, do not pay attention to quality management.
2, the quality of personnel Zhang experience, lack of capacity.
3, did not appoint a special quality management personnel.
4, there is no development and implementation of a reasonable, workable quality management plan.
5, the lack of quality specifications and quality standards.
6, there is no established quality assurance system.
7, quality control, do not get bit.

[Question 2] (5 points)
1, Project Management Plan
2, the quality measure
3, quality checklists
4, job performance data
5, approved change requests
6, deliverables
7, project files
8, organizational process assets

[Question 3] (4 points)

(1 pair

(2) wrong

(3) to

(4) wrong