The study notes scrum smoke - how to develop Sprint plan (Plan Meeting)

1. How to estimate how many story points we can do this sprint

1) instinct
 2) calculate the productivity
  estimate productivity / productivity actually
  look at the history of the team, look at their productivity over the past few years is how many sprint
  and then assume the next sprint in productivity almost
  This IS Also Called Yesterday's weather Weather
  
  Sprint's Focus Factor
                             [ the Velocity Actual]
  [the Focus factor] = ---------------------
                             [Man-Days the Available]
       
  EG:
  Last Sprint apos Focus factor:
                18 is Story Points
  40% = - --------------
                45 man-Days
    
  the this Sprint apos Estimated Velocity:
  50 Days man-X-20 is 40% = Story Points

 