SAP process route from entry to abandonment series - sub-process - Part2

overview

A subitem that belongs to an operation and is used for more detailed planning of the process steps described in the operation.
insert image description here
Sub-processes can only be used as capacity and cost calculations for detailed planning and cannot be used as data dimensions for scheduling and scheduling.
insert image description here
In the function of scheduling and scheduling, sub-process data will be displayed, but cannot be adjusted, only the main process can be adjusted
insert image description here

scenes to be used

Sub-processes can be used to assign multiple people or machines that are required at the same time to a process.
It can be set to calculate the cost of the sub-process, but it can only be planned relative to the parent process. Standard values ​​can be accumulated from sub-operations of the corresponding operation.
In the sub-process, you can set whether to copy the sub-process belonging to a certain process to the production order.

Sub-process content

Sub-actions can set the following data:

1. Maintenance process control code

Use the process control code to control whether to calculate the cost of the sub-process, whether the sub-process is self-made or outsourced, whether it is possible or necessary to confirm the work report after the order is processed

Configuration path: SPRO-production-basic information-process route-process data-definition control code

*After setting the scheduling parameters of the sub-process, the time cannot be directly changed in CM25
insert image description here
*Main process control code setting
If the operation value of the main process is cumulative, then do not check the success option
insert image description here

2. Maintain the salary type of the sub-process

3. Operating standard value

Maintain the activity type plan value to be performed in the suboperation.
insert image description here

4. User-defined fields

User-defined fields can be different from the main operation

5. After maintaining the job type data of the sub-process, click to summarize the standard value, and the job type value of the process can be accumulated through the sub-process

insert image description here

6. You can set whether the sub-process is brought into the production order

insert image description here

After checking, the sub-process of this process in the order field will not be brought into the production order

Precautions:

1. About component allocation

Material components, production resources/tools or inspection characteristics cannot be assigned to sub-operations, only to corresponding operations. When selecting a component assignment in an operation, sub-operations cannot be selected.
insert image description here

2. About job reporting

The sub-process can only enter the data of the standard value of the operation type, and cannot report the quantity of the process.