SAP KANBAN purchase and replenishment model from entry to abandonment series

1. Create material master data - MRP type is set to ND, no other special points

2. Create purchase information record (ME11)

3. Create a Supply Zone

 

 4. Create a procurement replenishment strategy

 5. Create a Kanban control cycle

 The reason PD01 cannot be selected here is because the material is ND, and the storage location K001 is not excluded from participating in MRP, so the system excludes it by default, so it cannot be selected.

 

Create an MRP area in the S4 system and assign it to a material, path: SPRO-Production-Material Requirements Planning-Master Data-MRP Area 

 Step 6, PK13N - Operational Kanban Status

Set the status to empty, the system will automatically create a purchase order, and the value of the Kanban related field is X

 Set to FULL, the system will receive the purchase order