Required questions:
(Actually, it's the kind that I can't remember after reciting it many times - embarrassing). . . . .
1. The claim process, the same additional 10%
2. What are the basic steps of the quality control process? ? ? ? ? ? (This really doesn't work o(╥﹏╥)o cry)
①Select the control object
② Determine the standard or target for the control object
③ Make an implementation plan
④According to the plan
⑤ Tracking, monitoring and checking the implementation of the project, and comparing the results with the plan
⑥ Find and analyze deviations
⑦ Take corresponding countermeasures according to deviations
3. Basic technical methods of project quality planning tools?
Cost-benefit analysis, statistical sampling, seven basic quality tools (which seven?), experimental design, cost of quality, other quality management tools, benchmarking, meetings
4. Measures to effectively shorten the construction period (5 steps, already met, not repeated)
5. Quality management process
① Determine the quality standard system
② Quality control of project implementation
③ Compare the actual with the standard
④Error correction
6. Claim Process
File a claim, submit claim materials, supervise response, ongoing claims, arbitration and litigation (28 days)
7. Change process?
(Blindly reciting) submit change request, assess change impact, CCB approve change, implement change, monitor change
8. Business changes (perfect measures), adapt to the future (preventive measures), if the development environment does not change (adaptive measures)
9. What are the main steps of the project feasibility study? (This is really not memorized)
① Determine the project scale and goals
② Study the running system
③ Establish a logical model of the new system
④ Export and evaluate various schemes
⑤ Recommend feasible solutions
⑥ Prepare a feasibility study report
⑦ Submit a feasibility study report
10. Main steps of project establishment
Preliminary Feasibility Study, Detailed Feasibility Study, Project Demonstration, Project Evaluation, Preparation, Submission and Approval of Project Feasibility Study Report
11. The basic content of quality assurance activities (I have been looking for a long time and do not know where)
how to establish quality standards,
How to establish a quality control process,
Propose the methods and techniques used in quality assurance
How to Establish Quality Assurance System
(Software testing is a traditional Chinese medicine for quality assurance)
12. Contract Management
Signing management, fulfillment management, change management, file management
13. Notes on contract analysis
Party's rights and obligations
Project cost and project payment
change convention
Liability for breach of contract
Quality requirements
The deadline for the construction unit to submit relevant information
14. What activities does configuration management include? (A lot, I don't know how to carry it)
Specify a configuration management plan
Identify configuration items and establish baselines
Build a configuration management system
Version management and release management
Implement change control
Report configuration status
Configure auditing
15. Software configuration management
(????)
16. Workflow of project management plan preparation (this still has to be recited o(╥﹏╥)o)
① clear goals
②Establish a preliminary project team
③Work preparation and information collection
④ Prepare a preliminary outline project plan based on templates and standards
⑤ Incorporate the above plans into the project plan, and then comprehensively balance and optimize the project plan
⑥ The project manager is responsible for organizing and writing the project plan
⑦ Review and approve the project plan
⑧ The approved project plan is the benchmark plan of the project
17. Team Improvement Suggestions
Communication training, improve team work environment, create team atmosphere, replace members, formulate clear organizational goals and work processes, formulate and implement various punishment measures
18. Specific responsibilities of quality assurance personnel in procurement
Whether the supplier is eligible
Whether the manufacturers participating in the competitive negotiation have the corresponding qualifications
Whether the purchased equipment meets the requirements
Possible Risk Prevention of Procurement Contracts to be Signed
19. Reasons for quality problems
Incompetence of project team members
Design quality is not high
Inadequate testing
Review does not follow specifications
Project review did not meet expectations
No organizational process assets
There is no good quality management plan in place
20. Give improvement measures from the perspective of quality management
Hire experienced technicians, re-test and revise bugs for each module until the quality requirements are met, conduct full integration testing and system testing according to the specifications, and strengthen the project review work
21. The main content included in the summary report
Project performance
technical performance
cost performance
progress performance
project communication
Identify problems and resolve problem situations
comments and suggestions
22. Documents handed over to customers after system integration is closed
System Integration Project Introduction
System Integration Project Final Report
Information System Instruction Manual
Information System Maintenance Manual
Software and hardware product manuals, quality guarantees, etc.
23. Suggestions for improvement of configuration management methods
Component Configuration Management Solution Design Team
Carefully understand the situation of the unit, historical personnel, organizational form, etc.
Effective evaluation of configuration management tools
Develop an implementation plan
Develop a comprehensive and effective configuration management plan
24. What processes are included before the project is established?
①Demand analysis
② Write a project proposal
③ Prepare a feasibility analysis report
④ Argument
⑤Assessment
25. Key Risks
technology, market, society, law, policy
26. Cost Estimation and Cost Budgeting
Contacts: Analogy Estimation, Parametric Models, Bottom-Up, WBS
the difference:
Cost Estimation: Approximate estimates of project activities, based on work packages, the output is a cost estimate
Cost Budgeting: The process of summarizing the estimates of all individual activities to establish a cost baseline, based on work package estimates assigned to time periods, the output is a cost baseline plan
27. Basis for overall change control (input)
Plans, performance, requested changes, completed deliverables
28. Overall change control is the process of identifying, documenting acceptance or rejection, and controlling changes to the baseline
29. Steps of Cost Budgeting
Break down work packages
decomposition activity
Break down time plan
30. Cost of the whole life cycle = development cost + maintenance cost + bidding cost + product replacement cost
31. Economic feasibility, mainly from the perspective of resource allocation to measure the value of the project
32. Contract management includes:
Contract signing management, contract performance management, contract change management, contract file management
33. The version control process of configuration items (this is also to be memorized, I have to laugh happily)
①Identify configuration items
②Establish a configuration management system
③ Create or issue baselines
④ Track changes
⑤ Change of control
⑥ Establish configuration management records
⑦ Perform configuration audit
34. Why version control of configuration items?
①It is conducive to unified management, avoiding version loss and reducing rework
②Conducive to the traceability of historical versions
③It is conducive to the coordination of development work
④ Make the configuration item in a controlled state
⑤Manage version conflicts
35. Project scope statement (this is also to be memorized)
①Project goals
②Description of product range
③ Project deliverables
④Project boundary
⑤Product acceptance criteria
⑥Constraints of the project
⑦ Project assumptions
36. What should be agreed in the contract
①Project scope
②Product model, technical indicators
③Project duration
④ Financial settlement method
⑤ Change method and process
⑥ Amount of project quality guarantee deposit
⑦ Product quality requirements acceptance process
⑧ After-sales service Chennuo and service expiration charges
⑨ Liability for breach of contract and how to resolve disputes