"Sit hot seat" ninth team work: Beta sprint preparation and acceptance
project | content |
---|---|
This work belongs courses | http://www.cnblogs.com/nwnu-daizh/ |
Where this requirement in the job | https://www.cnblogs.com/nwnu-daizh/p/11012922.html |
Team Name | Take the hot seat group |
Job learning objectives | (1) master the software black box testing; (2) learn to prepare software project summary PPT, project acceptance report; (3) the content control software project acceptance, and acceptance process. |
1. Project team github Address:
github Address: https://github.com/jessiyx/sethotchair
2. The members of the task today and tomorrow task schedule:
Names of Members | The current phase of the mission | The next phase of the mission |
Zhu Yi Xuan | Try to eclipes code directly into the server deployment | We continue to deploy tomorrow, hoping to complete it |
Xiao Wang | Today, I am responsible for the registration module test | We hope to complete the registration module test tomorrow, and start writing PPT |
Liu Zhenhua | Learning software project acceptance knowledge, making burndown | Tomorrow acceptance of the software project related work |
Of stars | Write blog, finishing the first day of issue encountered, and to assist in the deployment of code to complete eclipse | Continue to assist the deployment of code eclipes |
3. Members of the project's contribution to the number of hours today:
Names of Members | Accounting for the proportion of the workload of the entire job tasks | The actual time to complete their task (h) |
Zhu Yi Xuan | 27% | 5 |
Xiao Wang | 27% | 4.5 |
Liu Zhenhua | 23% | 3 |
Of stars | 23% | 3 |
4. Stand Meeting Photo:
5. Project burndown:
6. Summary:
Project drawing to a close, today's task abnormal heavy, it is especially hard. There is still a big problem in terms of technology, but we will continue to learn, strive to overcome!