Project: Solve the problem: How to edit the seven-day working day of the week in Microsoft project2016

1. Purpose

1.1 Thinking: How to edit the seven working days of the week in Microsoft project2016

2. Operation

2.1

Project --> Change Working Hours --> (For Calendar) Standard (Project Calendar) --> Work Week --> Details --> (Check "Sunday" and "Saturday") --> Set for the days listed The following specific working hours --> (enter the same start and finish time as other dates)

 

 

 