The daily practice and answers of the 2022 Supervision Engineer Case Analysis Examination will be compiled by the Youtibao official account according to the latest supervision engineer case analysis examination syllabus and the real questions of the supervision engineer case analysis examination over the years, including the key questions of the supervision engineer case analysis examination. With knowledge points, it is helpful for candidates to review the case analysis exam for the proctoring engineer and achieve good results.

 

 

1. For a project under supervision, the construction contract price is 150 million yuan, the contract duration is 18 months, the advance payment is 20% of the contract price, and the advance payment will be deducted from the monthly progress payment from the seventh month 3 million yuan will be returned until the deduction is complete, and the retention fee will be deducted from the first month at 5% of the progress payment.

In the fifth month of construction, the supervising engineer found micro cracks in the concrete poured in the third month. After inspection and analysis, the cause of cracks is due to inadequate concrete curing measures, and crack treatment must be carried out. To this end, the project supervision agency proposed: "Concrete works with microcracks are temporarily treated as unqualified projects, and the part of the project payment that has been paid in the third month will be deducted from the project progress payment in the fifth month. And the payment will be made the next month after the acceptance.” After calculation, the direct engineering cost of the concrete project is 2 million yuan, and the fee rate is: the measure fee is 5% of the direct engineering cost, the indirect cost rate is 8%, the profit rate is 4%, and the comprehensive tax coefficient is 3.41. %.

The construction unit entrusted a professional company with corresponding qualifications to deal with the cracks. The treatment cost is 48,000 yuan and the working time is 10 days. In the sixth month of the construction of the project, the construction unit filed an application for compensation of 48,000 yuan and an extension of the 10-day construction period.

The progress payment actually completed by the construction unit in the first 7 months of the project is shown in the table below.

question:

What is the project progress payment that can be signed and recognized by the project supervision agency in the first 3 months (considering the deduction of retention money)?

【Answer】

1. The project progress payment that can be signed and recognized by the project supervision agency in the first 3 months:

   The progress payment for the first month's signature = 2 million yuan × (1-5%) = 1.9 million yuan.

   The progress payment for the second month's signature = 3 million yuan × (1-5%) = 2.85 million yuan.

   The progress payment for the third month's signature = 5 million yuan × (1-5%) = 4.75 million yuan. The progress payment that the project supervision agency can sign and approve in the first 3 months:

   The progress payment for the first month's signature = 2 million yuan × (1-5%) = 1.9 million yuan.

   The progress payment for the second month's signature = 3 million yuan × (1-5%) = 2.85 million yuan.

   The progress payment for the third month's signature = 5 million yuan × (1-5%) = 4.75 million yuan.

The above are the daily practice and answers of the Supervision Engineer Case Analysis Examination. Xiaobian and Youtibao will continue to update the real questions and answer analysis of the Supervision Engineer Case Analysis Examination. Candidates should not miss it if they need it. I also hope that all candidates can achieve good results in the supervision engineer case analysis exam.

 

 