Remember a project experience (8)

The 7th week of the
project : 1. Project team members (products, front-end and back-end development, testing) should preferably work in the same area to facilitate communication and improve efficiency.

2. Methods to shorten the duration of activities:
2.1. Catch up on work, invest more resources or increase working hours to shorten the duration of key activities.
2.2. Fast follow-up and parallel construction to shorten the length of the critical path.
2.3. Use high-quality resources or more experienced personnel.
2.4. Reduce the scope of activities or lower the requirements of activities.
2.5. Improve methods or technologies to improve production efficiency.
2.6. Strengthen quality management, find problems in time, reduce rework, and shorten the construction period.