Fourth sprint
(1) SCRUM portion ☁️
Members Description:
Full name | Lixing Chen |
---|---|
Which completed the task | Without time to register Enter the phone number, the user is cautioned not enter a login name change |
Spent much time | 1.2h |
Also how much time remaining | 1.8h |
What difficulties | No difficulty |
The progress of these two days to solve | 2/2 |
Follow-day plan | Or continue to interface optimization |
⏳
Full name | Choi Tang Wei |
---|---|
Which completed the task | Resolve duplicate login issues, new exit feature |
Spent much time | 2h |
Also how much time remaining | 0h |
What difficulties | Little difficulty |
The progress of these two days to solve | completed |
Follow-day plan | no |
⏳
Full name | Chen Jiaying |
---|---|
Which completed the task | Scoring solve the bug |
Spent much time | 2h |
Also how much time remaining | 2h |
What difficulties | Scoring was done in a hurry, so there are many questions left, was not submitted only after a star rating of a button, jump or score did not return to the page, the user can repeat the score, has not echoed stars to the interface. |
The progress of these two days to solve | Cooperative solutions to the problem of non-repeatable scoring. |
Follow-day plan | Complete the scoring function test and modify the bug. |
⏳
Full name | Tan Wei |
---|---|
Which completed the task | Personal information center add a personal back-end |
Spent much time | 3 hours |
Also how much time remaining | 0 |
What difficulties | no |
The progress of these two days to solve | completed |
Follow-day plan | no |
⏳
Full name | Liu Ivan |
---|---|
Which completed the task | To exit function test |
Spent much time | 0.3h |
Also how much time remaining | 0h |
What difficulties | No problems were encountered |
The progress of these two days to solve | carry out |
Follow-day plan | Continue testing |
Screenshot development record
Test shots:
Home:
Such as increasing the exit after landing Home Online:
SCURM Conference Photos
(2) PM Report ☁️
Assignments progress
Assignments | 70 |
---|---|
Now spend time | 34.5 |
Also remaining time | 35.5 |
Burndown
Two days work summary
Halfway through the final stage of the beta version, we all work well together. But some members of the emergence of slack mood, it can understand, after all, a long time in the final stage everybody will feel tired. The next sprint I will first release a relatively simple task, so that team members who have a grace period. So the best time to sprint will be able to do everything.
Up to now have solved most of the bug needs to be modified, ongoing.