Class attribution | → 2019 autumn Charms practice of software engineering class Z |
---|---|
Work requirements | → Teamwork fifth - Project sprint |
Team Name | Light of the future |
The target job | On the sixth day of the sprint summary |
Text of the job | → Light of future- sprint Day 7 |
Other references | 1) two hours Getting spring boot Baidu cloud free resource: https://pan.baidu.com/s/11iD76gX1L_uF2nnhgx5wXA extraction code: 3yw8 2) SprintBoot Web Advanced Video 3) SpringBoot integrated JWT achieve token verification 4) Lay the classic ui module front-end framework 5) Bootstrap rookie tutorial 6) iBootStrap drag generated layout 7) About Web front-end password encryption is meaningful summary! 8) IDEA plug-in installation code specifications Ali 9) jQuery newbie tutorial 10) Project Manager essential - use burndown monitor the overall progress of the project 11) Project Management Tools - collar song |
1.SCRUM part:
Each member of progress
Names of Members | Progress description | waste time |
---|---|---|
Hu Chengyu | Today's schedule: perfect foreground to the background data transmission problems | 4h |
Wenjun Xin | Today's schedule: to continue to learn ssm succeeded in reading the data in the database, because mysql version I used was 8.2 multi-version, is inconsistent with previous versions connections, just kept on going finally figured out | 2h |
Lin Guoqin | Today's schedule: Learning the front-end interfaces to access back-end and back-end data is returned successfully received. During configuration, you need to pay attention to two points, one back-end interface address configuration, and second cross-domain problem. | 2h |
Huang Hung Penang | Today's schedule: training | 2h |
Zhangqi Rong | Today's schedule: Find the front and rear end interactive solution to the problem, as well as some code refactoring idea | 2h |
Ye Yanling | Today's schedule: understand the current front-end and back-end link problem, try to solve the problem of misaligned front page of text Order | 2h |
Wang Xing rain | Today's schedule: understand the current front-end and back-end link problem, try to improve the front page link issue | 2h |
Qiu Wei Xu | Today's schedule: Learning the front and rear, have a deeper understanding of the project | 4h |
Zou fluttering | Today's schedule: perfect background with back-end management module interface | 2h |
Wu Shanshan | Today's schedule: perfect background with back-end management module interface, complete the front page link issue | 2h |
Photo SCRUM meetings
Check-in record
Code run shot
Users browsing interface
Order Details interface
Administrator browser interface
New backend interfaces
2.PM report:
schedule
Expected number of days | The number of days already spent | The remaining number of days |
---|---|---|
7 | 7 | 0 |
Burndown
The total task curve
Than the contribution of each member
Crew | The proportion of the workload |
---|---|
Huang Hung Penang | 10% |
Lin Guoqin | 10% |
Wu Shanshan | 10% |
Zou fluttering | 9% |
Hu Chengyu | 13% |
Wang Xing rain | 9% |
Zhangqi Rong | 10% |
Ye Yanling | 9% |
Qiu Wei Xu | 10% |
Wenjun Xin | 10% |