SAP purchase order tax price display production program

SAP purchase order tax price display production program

 

Easily solve the SAP system procurement information metering in material prices can not save tax price issue

 

When we discuss price and supply, the majority of domestic suppliers prices are exclusive of tax, but we now maintain purchasing information is recorded in the system,

 

You can only enter without tax, so when you create a purchase order, will turn into after-tax price excluding tax price, many decimal places, resulting in price are not allowed.

 

Financial impact invoice verification, Printing affect print format appearance.

 

After the exchange of embodiment, forming four solutions:

1. When manually maintain purchasing information recording, using a calculator, the calculated net, and the net 1000x magnification, of about 90% can solve the problem;

2. manually maintain purchasing information records, you can use the "unit price", for example, the tax rate is 17%, enter 117 in the "unit price" (should be 1.17, because it is not a decimal, so the input 117), the net " price "at the input tax price, tax included expanded 100 times, for example, would have a price including tax material 950 yuan / ton, 95,000 now input, the input field is the use of net tax price! When calculating, 95,000 / 117, the net results.

3. Configure conditions in the purchase order types, the information recorded in the purchase in the "net" the input tax included, "unit price" is 1, the transit time of the division to use tax price of the purchase order, including tax calculated and net;

4. condition type disposed in the purchasing information record, in the "net" the input tax included, "unit price" is 1, increase "input tax", purchasing information recording saved turn into tax price. Then use multiplication in the purchase order to calculate the tax price and net material.

 

Since the project has been on the line, although the third kind and fourth solution is the best solution, but considering the amount of work and the success or failure related to the project, although tested successfully in a test system, not yet adopted.

The first and second parity scheme, in which the second scheme is most convenient, the information recording system already exists, to be modified at a later date.

Finalize the second option!

 

 