Group 11 Beta sprint (2/5)

Team Name

What team do not know

Leader blog

https://www.cnblogs.com/xxylac/p/11997386.html

Job blog

https://edu.cnblogs.com/campus/fzu/SE_FZU_1917_K/homework/10089

Project Status

Burndown

 

 

 

 

Chen Zheng Hua (Leader)

1. What are the last two days to complete the task:

  1. urge workers, strange pressure

  2. The front end module production process Canvas

  3. get SSL certificates and domain name

  4,code review

2. The next program

  1. Complete production module

  2. Learn about the canvas

3. What task left

  1. Complete production module

4. What are the difficulties

  1. The previous projects have not used canvas

5. Harvest and questions

  1. Learn to use the canvas

 

 Shen Yu

 1. What are the last two days to complete the task:
  1. Complete the search interface
  2. Complete the package template expression of crawling and interfaces
2. The next plan
    1. Optimize the performance of the interface
3. Which left the task
  No
4. What are the difficulties
  flask multithreaded but forget to lock the
5. harvest and questions
  thread and thread lock to learn

 

Li Zhenping

1. What are the last two days to complete the task:

  1. improve the front page of favorites

  2. docking interface and back-end collections

2. The next program

  1. improve the function Favorites

  2. Favorite curd filling into the front-end interface

3. What task left

       1. improve the function Favorites

  2. Favorite curd filling into the front-end interface

4. What are the difficulties

  Before the code amount is too small, there is no plan to write the code, improve code quality still

5. Harvest and questions

  And to understand the difference between synchronous and asynchronous difference JS

 

Chen Yi

1. What are the last two days to complete the task:

  1. Modify the home of some style

  2. Home of code components of (a collection of pop-up box integration as a component uses)

2. The next program

  1. improve the reporting function of page

3. What task left

  1. improve the reporting function of page

4. What are the difficulties

  No

5. Harvest and questions

   1. Understand what is a virtual dom

   2.mvc framework of principles and mvvm

 

Wang Zehong

1. What are the last two days to complete the task:

  1. Complete the reporting interface

  2. Understand the ngnix configuration

2. The next program

  Continue to complete Interface

3. What task left

  Continue to complete Interface

4. What are the difficulties

  Time is running out

5. Harvest and questions

  Harvest: Understanding the difference between http and https in

 

Lin Wei Zheng

1. What are the last two days to complete the task:

  1. Assist the head of the back-end interface to complete the preparation

2. The next program

  Write interface

3. What task left

  Write interface

4. What are the difficulties

  no

5. Harvest and questions

  no

 

Lin Yun-chuan

1. What are the last two days to complete the task:

  1. Edit ui interface design

2. The next program

  1. Assistance to improve front-end design of the page

3. What task left

  No

4. What are the difficulties

  For some color with a very fans

5. Harvest and questions

  Use a color wheel

 

Chen Jiawen

1. What are the last two days to complete the task:

  1.git use of learning

2. The next program

  Continue studying

3. What task left

  no

4. What are the difficulties

  Code is too bad, programming section not help

5. Harvest and questions

  Baidu continues to face learning

 

Wang Shi-ting

1. What are the last two days to complete the task:

  1.git use of learning

2. The next program

  Continue studying

3. What task left

  no

4. What are the difficulties

  1. multiplayer cooperative projects could not participate because of the strength of many

  2. The use of technology and other aspects are not familiar with

5. Harvest and questions

  1. Harvest: not understand the problem through Baidu to know, there is a deeper impression

  2. question: Programming is not familiar with the technical aspects

 

 

Latest results

    

 

 

 

 

 

 

 

 

 

 

Standup photo

 

 

 

 

 

 

 

N-meeting

Consuming (minutes)

1

7

2

8

 

 
 

 

 

 

Personal PSP

 

PSP2.1 Personal Software Process Stages Estimated time consuming (minutes) The actual time-consuming (minutes)
Planning plan 10 10
·Estimate • Estimate how much time this task requires 10 0
Development Develop 50 60
·Analysis · Needs analysis (including learning new technologies) 60 60
·Design Spec Generate design documents 60 60
·Design Review · Design Review 0 0
·Coding Standard · Code specifications (development of appropriate norms for the current development) 0 0
·Coding · Specific coding 120 150
·Code Review · Code Review 30 30
·Test · Test (self-test, modify the code, submit modifications) 0 0
Reporting report 60 70
· Test repor ·testing report 0 0
·Size Measurement · Computing workload 1 1
·Postmortem & Process Improvement Plan · Hindsight, and propose process improvement plan 0 0
  total 401 441

 

 

N-Week New Code (lines) Cumulative codes (lines) This week learning time-consuming (hours) Cumulative learning time-consuming (hours) Important growth
1 0 0 24 24 Preliminary master Axure Rp usage
2 300 300 10 34 The idea of ​​AI algorithms to complete thirteen water
3 300 600 15 49 Brainstorm a team project topics
4 1200 1900 15 64 Learn to analyze project requirements j
5 0 1900 5 69 For the actual programming carried out in advance of learning
6 500 2400 10 79 For a deeper understanding of the project team!
7 300 2700 5 84 分配任务
8 100 2800 5 89
9 200 3000 7 96 前后端交互
10 200 3200 7 103
11 300 3500 8 111
12 700 4200 12 123 promise的使用
13 200 4400 5 128
14 200 4600 5 133 canvas