The third work,

GitHub address
Teammate blog address
Teammate blog address
Job Link

PSP table

PSP2.1 Personal Software Process Stages Estimated time consuming (minutes) The actual time-consuming (minutes)
Planning plan 30 20
Estimate Estimate how much time this task requires 700 800
Development Develop 600 700
Analysis Needs analysis (including learning new technologies) 60 90
Design Spec Generate design documents 10 10
Design Review Design review (and colleagues reviewed the design documents) 10 10
Coding Standard Code specifications (development of appropriate norms for the current development) 10 10
Design Specific design 60 60
Coding Specific coding 300 500
Code Review Code Review 60 60
Test Test (self-test, modify the code, submit modifications) 180 180
Reporting report 180 180
Test Report testing report 90 100
Size Measurement Computing workload 15 15
Postmortem & Process Improvement Plan Later summarized, and process improvement plan 60 60
total 600 740