[Scrum] 2011/9/30 ----- ninth day

SCRUM Summary:

Team member

Yesterday’s Work

Today’s work

Issue

RX

Task 350: get pop up

Task 375: agenda item needs to remind folding and display a UI

DL H

Task 350: get pop up

Task 374:  When you exit the program should be saved to a separate storage in the data

TZ

@USTC


YY Z

Trial existing modules, suggestions comments

Trial existing modules, suggestions comments

N Z

Task 204: acquiring location information item, failure

Task204: change course, only to highlight the upcoming talk item by folding

No way by setting the screen focus to achieve the purpose of UI

HF L

@USTC

Task Burn Down:


  

                                           

Task Burn Rate:

Remaining work:

 

to sum up:

Daily Scrum ninth day, step by step, into the book task mop-up stage, there are two investigate the task has not to touch it, resulting in red require work, and today they close off.

 