Performance testing of scene design

Load Test

Demand For example:

The system 200 supports concurrent, user information query response time is less than 5 seconds

Scene design:

200 concurrent continuous operation for 20 minutes and test results verify the user information query response time is less than 5 seconds.

 

pressure test

Demand For example:

The operation of the system in concurrent 50,100,150,200

Scene design:

50 concurrent start every 10 minutes increasing to 50 concurrent, concurrent target 200, the target number of concurrent operation after reaching a further 10 minutes and then every 20 seconds stop 50 concurrent. By testing tool to monitor response times, transaction rates, the host resource usage, resource usage middleware, database operation.

 

Strength test

Demand For example:

The system can support a maximum amount of concurrent

Scene design:

100 concurrent, every ten minutes 100 concurrent increase, the number of concurrent target of 500, in the run for 10 minutes after the target number of concurrent arrival, if after reaching 500 concurrent system is still operating normally, continue to increase the number of concurrent testing. The event of a system crash or business a lot of mistakes in the process of increasing the number of concurrent, can be considered the greatest amount of concurrency is the current number of concurrent systems supported by testing tools to monitor response times, transaction rates, the host resource usage, resource usage middleware case, the database operation.