AI combat 2019-- 4th job (team hindsight meeting) - this name on it

project content
course AI combat 2019
Work requirements 4th job
Course objectives Learn the basics of artificial intelligence
The job helping me Review and summary
references Project Management - hindsight meeting


If you could start over, what aspects could be better?


"Just from the name of it" handwriting recognition project Postmortem results

Vision and goals

1. Our software to solve the problem? Whether clearly defined? Is there a clear description of the typical user and a typical scenario?
Software problems to be solved and the definition is very clear, which can make a clear description of the typical and typical user scenarios.

2. Is there enough time to do the planning?
Yes, but given scheme is too empty, no tasks assigned to each person and refinement.

3. The team at the planning stage is how to resolve the disagreement colleagues for planned?
The main chat resolved through micro letter, the other because we are too chicken dish, so for different opinions can not make an objective evaluation, most of them acquiesced.

plan

1. Whether you work planned eventually done? If you have not done, and why?
A lot of things did not finish, I think the real highlight of the last did not finish things, all projects. We underestimated the cost of time, really for doing too little time for this project.

2. You do not find some hindsight did not need or do not count for much?
Yes, but due to pre-mission refinement and tracking in place, so do a still better than not doing.

3. whether each task are clearly defined and measurable deliverables?
Most are not, because we really have not come up with enough time and effort.

4. The whole process if the project goes according to plan be?
No. For all the emphasis of this project is not enough, coupled with the level of technology limitations, progress of the project dragged on.

5. There are no plans to stay in the buffer, the buffer role it?
There is a buffer, an extended medium-term projects plays a buffer role to some extent.

Resources

1. We have enough resources to fulfill the tasks it?
Yes, the hardware resources courses offered very rich.

Time and other resources required for each task 2. How to estimate how accuracy?
Precision very rough, and later due to time constraints, project tasks increase, we can only try to make it complete, rather than precision.

3. User test of time, manpower and software / hardware resources are sufficient?
No user testing, human resources and hardware resources are sufficient.

4. Have you ever felt that you can do to let others do the (more efficient)?
Blog should be assigned to write about, so better to play a team strength.

Change Management

1. Each relevant employees in a timely manner that the message changed?
Micro-channel exchanges, each associated members can quickly know the change message.

2. What measures we have adopted a decision "to postpone" and "must be achieved" feature?
With the "silver bullet", in addition to leading to a brawl outside a short time, you can. Silver Bullet is a deterrent purpose.

3. The conditions of export project (Exit Criteria) whether the clearly defined?
We do not understand "export conditions" what is, after this one project, still do not understand.

4. For possible change whether contingency plans?
Basically no.

In summary

Our team in alpha stage to do a few functions with a relatively low level of method, beta phase or with relatively low levels of method, but also made several functions. The final bright spot features not implemented.