Problems to be considered in self-built computer room


1. Site selection: power supply, 220,000 volt substation, two.
Convenient transportation and easy post-operation and maintenance.
Ease of line intervention.

2. Civil construction: functional layer, with a load-bearing capacity of 800 kg per square.
If the height of the floor is more than 5 meters, it is necessary to reserve air-cooling space, the span is preferably large, and there is no block between modules.
Underground UPS, battery pack, large diesel engine, backup water cooling system.

Summary: To buy land, buy electricity, buy services, and consume air-conditioning dust.

3. Application for license, qualification (ICP, ISP certificate), application for dedicated power supply line (in addition, if you want to excavate pipelines, the distance from the substation that meets the requirements is far away, and you need to prepare for an investment of tens of millions of dollars just for power supply), data Transmission bandwidth, etc. (similarly, if there is no ready-made route for data transmission, it will be a large investment, and if you happen to pass through farmland, villages, etc., you must actively do a good job of the masses, everyone is good. Okay..).

Summary: Planning - Feasibility Study - Scheme Discussion and Approval - Preliminary Design - Procurement Bidding - Construction Drawing Design - Infrastructure Construction and Implementation - Hardware Equipment Arrival Installation - Software Development and Deployment - Module Commissioning - Joint Commissioning and Joint Test - Preliminary Acceptance - Test Operation - completion and acceptance are these stages, but the light infrastructure probably includes civil engineering, electrical, power supply, air conditioning, fire protection, security monitoring, lightning protection and grounding, decoration, transmission, etc. The new park is slightly better, old building renovation + original building If the blueprints, water and electricity plan drawings are missing, the seismic grade of the building should also be considered, and professional institutions should be sought for reinforcement testing and reinforcement design. There will be endless problems during the construction process. The technology and process are still relatively mature, but it is still difficult to say, otherwise why would BAT rent the operator's computer room?

That is to say, it requires the permission of the Ministry of Industry and Information Technology, the State Land Administration, the State Electric Power Administration, the operator and other competent departments, qualification review, and a deep relationship with the department heads. In addition, there must be very professional project construction leaders, BD managers, and so on.