One, Revit data processing
1. Add material library folder
If Autodesk Revit software is installed on this machine, you can point the folder to the software material library file (Note: the corresponding version 2.7 requires the version to be 2018 and above).
The default folder path of the general software is:
C:\ProgramFiles(x86)\CommonFiles\AutodeskShared\Materials\Textures\1\Mats, there are three folders 1, 2, and 3.
The adding location is shown in the figure:
if the machine does not have Revit software installed, you can copy the above material folder to the machine and add the association.
2. Georeferencing
2.1 Correction in Revit software
If you have the geographic coordinates corresponding to the base point of the Revit model project, you can modify the coordinates of the project base point in the Revit software to the actual geographic coordinates (projected coordinates). Please pay attention to the following points:
- The project unit needs to be modified to the corresponding unit, meter.
- The relative position relationship between the project base point and the model needs to be consistent with the actual position. If it is inconsistent, you need to calculate the moving base point to the corresponding position first, and then adjust the coordinates.
2.2 Registration in Pro
Define the coordinate system
To load data in .rvt format into Pro, you need to define the coordinate system. Use the Project tool to define the layer components:
Registration
Load the original .rvt data directly, use the manage and Georeference registration tool under the building tab to perform registration, and the operation layer is the Floorplan layer of the BIM data.
You can choose to move the model into the field of view, move, rotate, etc.
3. Packaged into SLPK data
-
Single rvt import: You can directly use the Create Building Scene Layer Package tool:
-
Multiple rvt needs to be put into one model: you can use it, BIM File to Geodatabase, Make Building Layer-Create Building Scene Layer Package:
Note: If you ensure that the model position is correct, it is recommended to package directly into SLPK data and view it in Pro, which can save The time when the rvt data entered the cache created by Pro.