Date: Apr 09th, 2020. The
content of the meeting is to complete the preliminary task division .
Scrum report
Progress
Team member | Be responsible for | Yesterday's progress | The next two days |
---|---|---|---|
Cookielau | PM, backend | Continue the practice of Django tutorial and blog integration and team task disassembly Contact the course center and information teacher related resource acquisition feasibility |
Realization of resource collection in the last 3 days of basic knowledge learning and guaranteed crawlers |
Liu zh | front end | Continue to study Vue.js tutorial and product prototype design | The last 3 days of basic knowledge learning and review of collected materials |
Feng mh | front end | Continue to learn, organize and collect Vue.js tutorial icon | The last 3 days of basic knowledge learning |
Fuji | front end | Continue to learn, organize and collect Vue.js tutorial icon | The last 3 days of basic knowledge learning |
Dz | rear end | Continue the Django tutorial exercises and front-end and back-end connection data collection | The last 3 days of basic knowledge learning |
Yang jc | rear end | Continue Django tutorial exercises and technical specifications writing | The last 3 days of basic knowledge learning |
Burndown chart
The first stage α burndown chart
completed the specifications and functions of the document, a little bit forward.
problems at hand
After contacting the teacher in charge of the course center, I learned that the course center is an outsourcing project. The outsourcing team did not provide the relevant APIs available, and it is difficult to meet our needs in the short term. We can only rely on ourselves to crawl or manually enter, which is for our The resource-demanding project is undoubtedly a fatal blow, but there is no way out of the sky. Through exploration, we found that crawlers can also automatically analyze and crawl the source code of the web page, but the problem is that it requires the unified authentication of students. Names and passwords are stored in plain text, and browsing the blogs of previous seniors and elder sisters reveals that the server has been hacked and the data is lost. This puts high requirements on the protection of user privacy. How can we carry out unified certification of the course center? It is a major difficulty to apply for the user's privacy information as little as possible.
Meeting record
Check in record
Complete the function and technical specification documents and check in the meeting minutes.
meeting content
WBS task teardown
- user
- registered
- Login
- Logout
- Modify information
- principal
- Publish DDL
- Here is the difference between the DDL issued by the person in charge and the DDL issued by the small group. The person in charge is the DDL of the assignment. The students who have chosen this course cannot refuse it.
- Can not refuse and mean no need to click to receive, reduce user disturb; can refuse to prevent harassment
- Publish DDL
- administrator
- Management Course
- Manage users
- Calendar / Agenda
- create
- delete
- modify
- Accept someone's invitation
- Mark complete
- Set reminder
- Resources (not an important task)
- Resource upload
- Download
Items completed in the first stage:
Numbering | task | principal | Complete time |
---|---|---|---|
1 | Django Tutorial Learning | rear end | 4.12 |
2 | Vue.js Tutorial | front end | 4.12 |
3 | Complete the user interface | front end | 4.16 |
4 | Complete database user rights management | rear end | 4.16 |
5 | Complete the calendar schedule interface | front end | 4.21 |
6 | Complete database calendar schedule management | rear end | 4.21 |
7 | Complete resource upload and download page | front | 4.25 |
8 | Complete resource upload and download management | rear end | 4.25 |
9 | Complete reminder function | rear end | 4.25 |
10 | Front-end connection | Front end | 4.19 |