How to draw a standard network time intuitive FIG.

FIG time scale network is a project network activity over the activity with the positioning and length. It is a bar chart containing the logic network, and any item in working position and represents the length of the duration of the network of FIG. Circle project manager



  When scale network diagram, the solid line arrows represent the work, the horizontal projection of the length of the solid line arrow indicates the duration of the job; dashed arrows represent the imaginary line of work, because the duration of the zero virtual work, it is only an imaginary line arrow Videos can be vertical; the wavy line indicates in its work immediately after the time interval between the work (except for the destination node to node is completed, when the planned duration equal to the calculated period, the length of the horizontal projection of the work arrow wavy line indicates that free float). Alliance project manager

  FIG time scale network planning so formed has both the advantage of network planning, but also has the advantage of intuitive Gantt program, the network program time parameter will visually expressed. Circle project manager

  Time Scale Network Plan should be prepared in accordance with the earliest start time of the work. For this reason, when preparing network planning should be marked so that each node and each work (including virtual work) on the left as far as possible, until the wire does not occur until the reverse arrow from right to left. Alliance project manager

  Before the preparation time scale network planning, you should press time unit has been established to draw upon standard network schedule. Time coordinates can be marked on the top or bottom of the time scale network schedule. When large-scale network planning, and more complex, you can mark time while the coordinates on the top and bottom of the time scale network schedule. If necessary, it may be simultaneously filling calendar time on top or bottom of the time coordinate under time coordinate. Transfer from Project Managers Union

  Preparation time scale network planning should be drawn when there is no underlying network plan sketch, draw, and then press the indirect or direct drawing method. Alliance project manager

  Indirect rendering method Project Management Forum

  The so-called indirect rendering method is a method to calculate the time according to the subject without the network parameters and determines the key plan sketch line, and then drawn at scale network planning table. Should be drawn first of all nodes positioned at their earliest time scale network planning table corresponding position, and then use the predetermined line (the solid line arrow and an imaginary line arrows) drawn to scale work and dummy work. When the length is insufficient to reach some of the work is completed Arrows node of the work shall be made up with a wavy line arrow should be drawn at the connection node of the work is completed. bbs.mypm.net

  Direct rendering method Alliance project manager

  The so-called direct drawing method is a method does not calculate the time parameters and the underlying network planned by the absence of direct sketching Time Scale Network Plan. Alliance project manager

  1. The source node is positioned at the start of network planning graticule line network timing schedule. Project Management Forum

  2. Press the duration of the work plan drawn at the starting point of a network node as the start node working Arrow. Alliance project manager

  3. In addition to the starting node network planning, after all other nodes must complete node to node work arrow lines are drawn, positioned at the latest in the line of work Arrow Arrow ends. When the length is insufficient to reach some of the work of the Arrows node shall make up the wavy line with arrows drawn in connection with the node. Alliance project manager

  4. When a node after the position is determined, in order to draw the working AOA node as the start node. blog.mypm.net

  The above-mentioned method to determine the position of each of the other nodes from left to right, until the destination node is depicted in network planning. Alliance project manager

  When drawing time scale network planning, especially problems that need attention, deal Dummy Arrows. First, the solid line arrow should the imaginary line arrows equated, but the duration of which corresponds to the work of zero; secondly, although it does not have a duration, but there may be a wavy line, and therefore, according to a predetermined draw a wavy line. When the wavy line in the drawing, it should still be drawn as a dashed line vertical portion.