Interface testing:
Appearance (inside, outside) aesthetics
Elevator whether spatial dimensions and consistent design size
Buttons are clear and easy to understand
Whether the display floor display
function test:
Test elevator can achieve normal function of rise and fall, whether each can be docked.
Each stopping floor of the floor coincides with the press
When the button is pressed the elevator button lamp is lit.
Whether the elevator is possible to effectively apply the upstream and downstream of each floor
Elevator full load time, whether or not ignore the other floors external uplink and downlink applications
Whether the elevator buttons can be used on both sides, three buttons.
Select whether the floor of the elevator can cancel the elevator doors opened, closed, normal close (automatically turn off).
Alarm device is available.
(Full load) whether overweight can be forced to close again move about whether overweight people up and down the line between whether the addition of an elevator and a good collaboration.
(Algorithm) elevator lighting meets the requirements of reading to contact the outside world how ventilation phone is available, whether when many people will be hot, poor ventilation (fan)
Elevator is available inside the camera, filming is clear
Door clip does not reach the people, it should not be forced to close and insider administrators can call on various occasions, can be forced to open the door when you run, you can not press the button to open the door, it does not force open the door in different situations (such as: block someone the immediately closed when power when not requested when ...), has closed the door key and a key from the outside elevator can be forced open
Test at different temperatures:
Enter the elevator, call the phone, whether a signal into the elevator propaganda, whether outside could hear
The display shows whether the floors, and the elevator down state correctly
Can I use two elevators (or disable)
Which one to use, whether another can be deactivated
A lift according to uplink, B lift up by
A lift according to uplink, B elevator press OK
A lift according to uplink, B by the elevator up and down
A lift according to uplink, B press the up elevator
A lift press line, B line press Elevator
A lift press line, B by the elevator up and down
A lift press line, B press the up elevator
A press up and down the elevator, B by the elevator up and down
A press up and down the elevator, B press the up elevator
How to run when empty elevator
Not into the elevator when the elevator door opened, after entering the elevator does nothing
The elevator door opened and the length of time, whether self-closing after more than time
Opening and closing elevator door time after the final timeout to 2 cm, can pry open the doors of an elevator door
After closing has not been rising, pressing outside of an elevator uplink (or downlink) whether the button, the elevator door will open
Lift the bottom of whether there is an elevator down button
Is there a button up top-level dock
Algorithm testing:
When the two are idle, take the principle of proximity, people take the elevator from the nearest elevator priority operation;
There runtime to peer direction and drop operation priority of an elevator, or free elevator arrangement;
2 are running, and on the way in the direction of passage of the elevator run priority;
Case each elevator, inside the elevator rise and fall in each process, and then lift each internal docking application of each elevator on each floor, in each rising and falling process, then no internal application within the elevator, in are each outside the elevator stops each elevator application, rise and fall in each process, and then inside the elevator stops at each application are inside the elevator, the elevator also applied outside each elevator stops at a floor would, if someone press 18 floor, then the elevator up to the fifth floor, someone pressed the 10th floor, whether this time will stop and the elevator down to display at full strength when 10 layers on the 10th floor, at this time if the 8th floor was waiting for the elevator, whether in the 8th floor stop.
Similar testing random test step 7-8, in the case of elevators have different combinations of internal and external application, verify the accuracy and reasonable floor landing.
Stability of the elevator, will rise or fall too quickly, causing the body not suited reaction
reliability:
No application, they can stay long in one layer, and the door is closed shut the door the moment there is an obstacle.
In the long term there is an obstacle blocking the door, the elevator should not be closed, or the rise and fall simultaneously press a button to open the door and close the door.
Press the button to open the door to close rapidly alternating current floor number clicks. After a quick click on different floors rise to the top, down the original request elevators will be canceled after the floor fell into the negative, the original request upstairs in the elevator outside the elevator will be canceled simultaneously pressing the UP and Down button will happen .
Press the button to open the elevator door remains open whether the case when a sudden power failure or overload, the elevator (stop, is on the rise, are falling) does not fall, the elevator doors can be opened by external force, and emergency phone available elevator operation, apply immediately to after stopping the floor, the elevator should not be docked.
Jumping in an elevator, the elevator will not appear unstable situation. Elevator operation of the elevator in the case of voltage instability does not work when there is monitoring whether the system automatically alarm when the elevator is not working properly, if there is a precise process can be assigned to all the people of the efficient handling Troubleshooting
Ease of use:
Design elevator buttons in line with the general habits of people use it.
Button is considered disabled and small children
Floor display is in the upper part of the elevator, so people can see
Maintainability:
Is there a convenient elevator repair and maintenance of working conditions (access shaft, unified power failure, etc.)
Elevator Common accessories are easy to replace
How elevator maintenance costs of the elevator installation, maintenance, testing, maintenance over life, whether the normal operation