Third job: Pair Programming

Personal third job: Pair Programming

Github project address https://github.com/mengcc1/PairProgramming.git
Twinning partners work address
Job Link https://www.cnblogs.com/cherish599/p/11577268.html

Specific operations

Form a .PSP

PSP2.1 Personal Software Process Stages Estimated time consuming (minutes) The actual time-consuming (minutes)
planning plan 60m
· Estimate • Estimate how much time this task requires 3-4d
Development Develop 1-2d
· Analysis · Needs analysis (including learning new technologies) 1d
· Design Spec Generate design documents 1h
· Design Review · Design Review (and his colleagues reviewed the design documents) 1h
· Coding Standard · Code specifications (development of appropriate norms for the current development) 5h
· Design · Specific design 2h
· Coding · Specific coding 5h
· Code Review · Code Review 1h
· Test · Test (self-test, modify the code, submit modifications) 3h
Reporting report 2h
· Test Report · testing report 2h
· Size Measurement · Computing workload 2h
· Postmortem & Process Improvement Plan · Hindsight, and propose process improvement plan 2
total

II. Problem-solving ideas description

1. Under to discuss and determine the two of us need to do

III. Calculation module design and implementation of the interface

IV. Code review process

V. display calculation module of the unit test

VI. Code Description

VII. Experiences

First of all, I felt the joy of cooperation among the fun and harvest of cooperation. But also aware of their many deficiencies, including inadequate programming techniques, a lack of understanding of the code, get a lot of knowledge from partner there. Teamwork exercise their own, it would also reflect their own very real problem, it is a good way to improve your own.