Third job: Pair Programming
Others
2019-09-30 16:55:14
views: null
Personal third job: Pair Programming
Specific operations
Form a .PSP
planning |
plan |
60m |
|
· Estimate |
• Estimate how much time this task requires |
3-4d |
|
Development |
Develop |
1-2d |
|
· Analysis |
· Needs analysis (including learning new technologies) |
1d |
|
· Design Spec |
Generate design documents |
1h |
|
· Design Review |
· Design Review (and his colleagues reviewed the design documents) |
1h |
|
· Coding Standard |
· Code specifications (development of appropriate norms for the current development) |
5h |
|
· Design |
· Specific design |
2h |
|
· Coding |
· Specific coding |
5h |
|
· Code Review |
· Code Review |
1h |
|
· Test |
· Test (self-test, modify the code, submit modifications) |
3h |
|
Reporting |
report |
2h |
|
· Test Report |
· testing report |
2h |
|
· Size Measurement |
· Computing workload |
2h |
|
· Postmortem & Process Improvement Plan |
· Hindsight, and propose process improvement plan |
2 |
|
|
total |
II. Problem-solving ideas description
1. Under to discuss and determine the two of us need to do
III. Calculation module design and implementation of the interface
IV. Code review process
V. display calculation module of the unit test
VI. Code Description
VII. Experiences
First of all, I felt the joy of cooperation among the fun and harvest of cooperation. But also aware of their many deficiencies, including inadequate programming techniques, a lack of understanding of the code, get a lot of knowledge from partner there. Teamwork exercise their own, it would also reflect their own very real problem, it is a good way to improve your own.
Origin www.cnblogs.com/LLXx19991229299/p/11612100.html