Normally, when we talk about resource costs, means that the cost-based rates of resource personnel and materials. Cost resource is a resource cost "fixed" type, such as the cost of equipment or personnel needed for one-time resource costs (travel expenses), unlike the fixed cost for the task input, resource costs need project leader \ manager resources work " table "input on resource costs, and assign it to the task, with different personnel or material resources, when assigned to tasks, resources, costs will not affect the schedule.
New product development, for example, describes the specific steps on how to enter resource costs:
1. Open the "New product development .mpp file", click on "View" -> "Resource Sheet", as shown below:
Note: If you do not see "Item" table, click on "View" -> "Table" -> "item", as shown below:
2. Resource worksheet, enter the name of the resource cost, such as tickets, in the "type", select "cost", as shown below:
3. Click the "view" of the -> "Gantt Chart", as shown below:
4. In the Gantt Chart list, select the "demand discussion of the mandate" and assign cost resources: ticket, click "OK", as shown below:
5. In the tool bar, click on the "View" -> "task allocation", as shown below:
6. Select "needs to discuss" right-click on the "information", as shown below:
7. In the Task Information dialog box, click on the "Resources" tab in the "ticket" cost resource input costs Amount: 4000, click "OK" ,As shown below:
8. In the Gantt chart list, click Add a new column: The costs associated with each task you can see the amount of resource costs and the total cost, as shown below:
Description:
Cost Amount • Cost resource is not assigned the task has been completed affect the amount of work.
· If you add the cost of the amount of resources on a date other than the current start or end date of the mandate, the Project will adjust the start or end date to the date of the cost of resource allocation include, for example: if the task starts on June 26 , ending July 9, while the project manager resource input costs in the amount of 11 July ¥ 5000, the end date of the task will be July 11, as shown below: