Schedule agreement and Delfor

Here we look at the forcast BVS factory in France to Chinese factories.

step1. BVS first created in a factory there forcast SA. vendor = CHC plant. here there is only one of a SA Material no.

image

In the item detail can be seen inside information in the info record maintenance

image

Click to enter additional data.

image

This field can see the firm zone, where maintenance is calander date. That is from the SA release creation date + count this time, schedule delivery line in this range can not be modified.

image

Another way in which SA Although the firm zone is empty, but inside the planning time fence MMA has a value (here is the work day), then when running the MRP, delivery schedule within this range will not be automatically update.

image

STEP2: Save the SA. ME38 Create a delivery schedule.

image

Here's delivery date refers to the date of receipt of the French BVS.

STEP3: IDOC Configuration

image

3.1 orders: create a trading contract factories in China CHC's.

image

Here Application select EV

imageimage

3.2 ORDCHG modify the order, message type YAED.

image

Sometimes the message type and creation time can be used is the same, but the change is needed √ marked.

image

3. DELFOR needs to send updates.

image

The app = EL.

image

.. STEP4 send orders to factories in China CHC ME33L go - "healder-> message

image

We can see the orders there is no information shcedule line is.

image

STEP5, send DELFOR update plan

Because SA Release by weekly created so, start EDATUV = week, EDATUB = week's end.


image

STEP6- Chinese factories CHC T / C, is also only one part number. Correspondence with SA.