Softgong Network 15 Teamwork 4 - Agile Sprint 3.0 in Alpha Stage

Softgong Network 15 Teamwork 4 - Agile Sprint 3.0 in Alpha Stage


1. Hold a stand-up meeting every day, and provide a photo of the stand-up meeting on that day.

2. Yesterday's progress, existing problems, and today's arrangements for each member of the project.

  • The work completed yesterday:
    (1) Completed the construction of the server;
    (2) Completed the construction of part of the database;
    (3) Completed the design of the entry interface;
    (4) Completed the dynamic interface of my punch card.

  • The work planned to be completed today:
    (1) Completed the design of some new topic pages;
    (2) Completed the design of some of my settings pages;
    (3) Completed the design of some of my topic records;
    (4) Completed the construction of the database.

  • Difficulties encountered in the work:
    (1) Today's task is mainly a buffer transition. Due to the influence of difficulty and time, the progress is a little bit behind. Today is to complete the unfinished part assigned on the first day.
    (2) For us, it is difficult to learn a new language while designing the interface, and the speed of the front-end is also slow.
    (3) On the one hand, the process of WeChat applet development is unclear and incomprehensible, which makes the back-end somewhat incomprehensible.

3. Publish the project burndown chart.

4. Code cloud project management records, code/document check-in records.

5. A recent (running) screenshot of the appropriate project program/module.

6. Daily summary.

Guo Weicheng: Zheng
Xiaoli:
Liao Yijie: Although I seem to be getting started more than the previous two days, writing code is still quite bumpy. Every time I compile it, there are many situations. Sometimes the code is obviously changed, but the result remains the same. , so I have been trying and trying, and I feel that the atmosphere of a whole team learning new things together is very good, I like this kind of environment very much, and I hope to stick to it.
Bao Mengrong:
Ke Zhiqing:
Huang Xiaoyang: Because some databases were built yesterday, my main task today is to build the database, write a blog, and discuss the back end of the project with my teammates in charge of the back end. , to clarify the entire project process. Although the effect is not large, but there are gains. I hope we can gain more things in the follow-up development. It is not necessary to do this project very well, but we must cherish this process.